Project Details
The project is located at King Abdullah II Street intersection with Wasfi Al Tal Street and it consists of a lower tunnel with a length of (470 m) and width of six-lane and overpass with a length of (490 m) and width of four lanes, the project includes a circle along with rotary movements with the wrap and pedestrian passages as well lighting, walls, waterwheels, pots of flowers in addition sewer lines and storm water drainage, electricity and communications, The project was implemented in record time during the period (140 days) before the deadline for its extradition.